A
compulsive obsessive desire to ignore the lessons of history is slowly choking
us.
If
Tasmania is to become a renewable energy powerhouse, shouldn’t we have some
understanding how existing wind farms and the Basslink interconnector work, who
profits and who pays?
What’s
the difference between regulated and unregulated interconnectors and what are
the ramifications of the termination of the Basslink Services Agreement
announced on 10th February, an agreement covering an interconnector
that was supposed to have a life of 60+ years but is falling apart after only
15 years.
Without
stopping to analyse what went wrong with Basslink we seem to be careering ahead
to build an even more expensive one, whilst the State refuses to face up the
underlying fiscal sustainability of a government which is gradually falling behind in attending
to its core functions.
At
the centre of energy policy is a Minister who is the shareholder minister in charge
of Hydro, TasNetworks and the retailer Aurora Energy, and who pretends he is
able to seamlessly resolve any conflict between competing parties whilst also looking after the interest of renewable energy proponents, consumers and Tasmanian
taxpayers.
If
it sounds too good to be true that's because it is.
Basslink
profitability
We’re
on the brink of having another interconnector foisted upon us but neither the
government nor Hydro Tasmania are prepared to tell us the profitability of the
existing Basslink cable. The annual report tells us the quantity of electricity
imported and exported but that’s it. How much money is made from the importing
and exporting? Given the proposed Marinus cable will have three times the
capacity of Basslink it would be useful to know. All we know from Hydro’s
annual report is that it’s becoming harder to make money. Budget forward estimates suggest lower
profits in the future from Hydro.
The
info which the government/Hydro prefers wasn’t discussed is all publicly
available. Both AEMO, the Australian Energy Market Operator and AER, the
Australian Energy Regulator publish masses of data. AEMO manages the NEM, the
National Electricity Market and strives to recover costs from all participants.
AER has a monitoring and enforcement role and perhaps most significantly sets
network prices. OTTER, the Office of the Tasmanian Economic Regulator sets
retail prices and has a regulation and monitoring role in the wholesale market.
OTTER
publishes the $ value of Basslink imports and exports weekly. Here’s an example,
covering NEM week 52 from 19th to 25th December 2021.
Exports
for the week were 18.33GWh and imports 40.32 GWh. The $ revenue was $481,280
from exports and $1,469,350 from imports giving total revenue of $1,950,630 for
the week.
Over
the 52 weeks from 28th Jun 2020 to 26th June 2021, NEM
reported total BL exports of 1,021 GWh and imports of 1,612 GWh. (NB Hydro’s
2021 Annual Report reported BL exports of 1,007GWh and imports of 1,612 GWh for
the financial year 2020/21. The minor difference in the export figure is almost
certainly due to the financial year being a slightly different period from the
52 weeks covered by the NEM figures).
The
revenue (or inter regional revenue as it’s more correctly called) from BL for
the 52-week period was $42 million from exports and $31 million from imports,
for a total of $73 million for 2020/21. That implies exports averaged $41 per
MWh and imports $19 per MWH.
To
understand what this means a bit more background is needed.
The
BL interconnector, owned and operated by Basslink P/L but currently in
receivership, generates revenue in a similar way to
generators in the NEM, by bidding into the spot market its capacity to deliver
energy, with the returns determined by the price difference and the energy
flows between Victoria and Tasmania. These returns are the inter-regional
revenues. Under the arrangement with Hydro pursuant to the Basslink Service
Agreement (BSA), Basslink as the owner/operator of the interconnector agreed to
swap the inter-regional revenue for an agreed fixed facility fee, plus
performance-related payments covering availability adjustments and commercial
risk sharing. The agreement also gave Hydro the rights to control the way in
which Basslink bids its interconnector capacity, either flowing in or flowing
out of Tasmania.
On 10th February Hydro decided to terminate the BSA.
Minister Barnett implied the recent lengthy arbitration proceedings which
determined the cable was unable to perform as required, led to the termination
decision. But there was likely much more to the story than that. (More about this
can be found below in the section Termination of BSA).
Even though the BSA has now ended it is useful to understand how
it worked. Basslink P/L receives a weekly payment from NEM representing a
week’s worth of inter-regional revenues. Inter- regional revenue, whether from
exports or imports is a net figure. In the case of exports, Basslink P/L buys
electricity from a Tasmanian generator (almost certainly Hydro) and sells it
into the Victorian market. NEM will collect the sale amount, pay the Tasmanian
generator for the purchase and remit the balance being the inter-regional
revenue to Basslink P/L.
Under the BSA, Basslink P/L then forwarded the inter-regional
revenue to Hydro and Hydro paid Basslink P/L the facility fee plus the
performance adjustments each month. The inter-regional revenues were legally earned
by Basslink P/L, as operator of the cable, but were included as Hydro’s income pursuant to the BSA
arrangement. Basslink P/L included the facility fee as income and paid all the
operating expenses associated with the interconnector.
Hydro also pays Macquarie Bank a monthly fee which represents
costs incurred by Hydro when it was sweettalked into a hedging arrangement with
Macquarie Bank to protect it from interest rate rises during construction of
the link and from interest rates embedded in the facility fee. Rates have since
plummeted. The hedging arrangements adds roughly another 50 per cent to the
facility fee which means Basslink currently costs Hydro about $125 million per
year. That is confirmed by the Basslink current liabilities of $125.8 million
listed in Hydro’s books as at 30th June 2021. A current liability is
one expected to be paid in the next 12 months.
Hence Hydro has needed to earn a lot extra to pay the fees. As
we have seen total inter-regional revenues for 2020/21 were $73 million. This
is before the losses from transmission over the BL cable of approx 3 per cent
plus another 1 per cent when electricity is converted from alternating AC to
direct DC at the beginning of transmission and vice versa at the other end of
the cable. Total transmission losses are estimated to be about 5 percent which
means Hydro probably made $70 million from BL trading in 2020/21. Hydro’s
financials recorded expected inter-regional revenues as financial assets. The
amount listed as a current asset, in other words expected in the next 12
months, was $64 million for the 2020/21 year. The actual inter-regional revenue
received for 2020/21 was likely to have been $70 million. With costs of $125
million, that’s a big loss.
Money is made importing and exporting. The precondition for making
profits are the different spot prices in Tasmania and Victoria.
The following table shows the average quarterly spot prices since
1st July 2020.
Average
quarterly spot prices |
|
|||
NEM
quarters |
Unit:
$/MWh |
|||
|
VIC |
TAS |
Difference |
|
2020 Q3 |
July 20 to Sept 20 |
54 |
51 |
3 |
2020 Q4 |
Oct 20 to Dec 20 |
40 |
46 |
-6 |
2021 Q1 |
Jan 21 to March 21 |
27 |
34 |
-7 |
2021 Q2 |
Apr 21 to June 21 |
77 |
47 |
30 |
July 21 to Sept 21 |
64 |
27 |
37 |
|
2021 Q4 |
Sept 21 to Dec 21 |
33 |
30 |
3 |
Note:
The NEM year is a calendar year
The
table is just a snapshot of average spot prices each quarter. There is a lot of
variation within quarters, from day to day and from hour to hour. Care need to
be taken when drawing conclusions. But where Vic spot prices are well in excess
of Tas spot prices as occurred in 2021 Q2 and Q3, electricity will be exported
to Vic. The exports in 2021 Q2 for instance, only represented 17 per cent of BL
flows (both export and import) for Hydro’s 2021 year but they earned 38 per
cent of inter-regional revenue for the year. The pattern continued for the next
quarter 2021 Q3, covering July to Sept 2021 (the first quarter of Hydro’s 2022
year).
The
earlier two quarters in the 20/21 year (2020 Q4 and 2021 Q1) saw Tas spot prices
exceeding spot prices in Vic. This led to more imports during those quarters,
accounting for 30% of inter-regional revenue for 20/21. Imports and exports for
the rest of 20/21 weren’t significant in $ terms. The following table has the
figures, prices and quantities, for inter-regional revenue.
NEM quarters |
Exports |
Imports |
|||||
|
Amount GWh |
Value $m |
Av per MWh $ |
Amount GWh |
Value $m |
Av per MWh $ |
|
2020
Q3 |
July
20 to Sept 20 |
287 |
6.5 |
23 |
332 |
5.3 |
16 |
2020
Q4 |
Oct
20 to Dec 20 |
180 |
5.7 |
32 |
461 |
11.2 |
24 |
2021
Q1 |
Jan
21 to Mar 21 |
111 |
1.7 |
15 |
577 |
10.4 |
18 |
2021
Q2 |
Apr
21 to June 21 |
444 |
28.2 |
63 |
242 |
4.0 |
16 |
2021
Q3 |
July
21 to Sept 21 |
581 |
33.1 |
57 |
173 |
3.1 |
18 |
2021
Q4 |
Oct
21 to Dec 21 |
383 |
8.8 |
23 |
285 |
7.4 |
26 |
Just
to reiterate, the revenue figures are not the gross revenue received, but
rather the differences between the spot prices in Vic and Tas. Basslink P/L buys in one market and sells in
the other. NEM pays it the difference each week. In the case of exports, it’s
the extra earned by exporting to Vic compared to selling on the spot market in
Tas.
Going
back to the table of average spot prices, another striking feature is the low
Tas spot price in 2021 Q3 from July to Sept. As the Australian Energy Regulator
AER noted in its quarterly report, this was the lowest quarterly price for any
of the five NEM regions since 2012. (NB The regions are Tas, Vic, NSW, Queensland
and SA). The low figure was probably caused by favourable rains over winter and
spring in the northern and western rivers in Tas and the increased electricity
from wind with Cattle Hill and Granville Harbour wind farms now fully
operational. The additional wind capacity which has doubled Tasmania’s
electricity from wind from 10 to 20 per cent of our needs, will likely put
downward pressure on Tas spot prices and make importing electricity a less
attractive proposition. Hydro power can reasonably comfortably supply the other
80 per cent.
The latest AER quarterly report covering July to Sept
2021 also noted spot prices declined in every NEM region. There was a record number of negative prices in
every region. In Victoria prices were negative 22% of the time. Under NEM
rules, wholesale prices can fall as low as negative $1000 a megawatt-hour,
meaning in theory generators have to pay to deliver power into the spot market.
Prices generally fall into the red around the middle of the day when wind and
solar generators and coal power plants are competing to dispatch their energy.
There’s not much point sending electricity into a market with negative prices
but stopping and restarting generators can be even more costly. One of the
market responses to negative prices is to instal batteries with the aim of
withholding electricity from the market and waiting for a better price. This is
now occurring on the mainland. Many will remember then Treasurer Scott Morrison
pooh-poohing Tesla’s large battery proposed for South Australia back in 2017:
“"I mean, honestly, by all means have the world's
biggest battery, have the world's biggest banana, have the world's biggest
prawn like we have on the roadside around the country, but that is not solving
the problem.”
People making investment decisions disagreed. Batteries are
becoming more widespread, even being proposed to run alongside aging coal-fired
generators hoping to get a few more years of use before they go the way of
dinosaurs. Batteries will tend to lower price variations, the very thing which has
made exporting to Vic via Basslink a profitable (at times) activity for Hydro.
Lower spot prices and smaller differences between Tasmanian
and Victorian prices were looking likely to impact Hydro’s profits. The forward
estimates in the Budget papers showed payments from Hydro to the government (income
tax equivalent payments and dividends) declining in real terms.
A doubling of electricity from local wind generators has
already lessened the opportunities to import electricity profitably, and the
increasing use of batteries on the mainland will lessen the opportunities to export
electricity profitably. That’s been Hydro’s dilemma. Casting a giant shadow
over Hydro was another 10 years of Basslink where costs of $125+ million per
annum would have coincided with inter-regional revenues of about $70 million
per annum, but under increasing pressure. Some of the shadow may have been
removed with the decision to terminate the BSA. (More on this below in the last
section headed Termination of the BSA.)
Paradoxically the Marinus interconnector would likely make it
even harder to profit from the arbitrage advantages that arise when spot prices
in Tasmania and Victoria differ. By its very nature a regulated interconnector will
reduce arbitrage advantages that may exist between NEM regions as the costs and
benefits of a regulated connector and are spread across all network users. Diminished
arbitrage advantages across the network are inevitable.
One doesn’t expect Hydro or the government to shout about
Basslink’s unprofitability from the rooftops. But the kneejerk response to
claim commercial-in-confidence at every turn rather than assist the
understanding of publicly available information is a step too far in a world
where the peddling of falsehoods is becoming the norm rather than the
exception.
As we will see below, another reason the government and its
electricity businesses don’t want to dwell too much on the financial lessons of
Basslink is because they see themselves building a completely new electricity
system for the 2030s. TasNetworks’ new Chair Roger Gill made this clear during
the December 2021 Leg Co scrutiny hearings. Planning for the future is
commendable but that shouldn’t mean ignoring past lessons. If Tasmania is going
to produce twice as much energy as it needs surely some understanding of how
trading via the current interconnector works, what are the problems and how
will the new electricity system make it better.
Regulated vs non-regulated interconnectors
There are currently three major interconnectors in the NEM…..
Basslink, Murraylink and Directlink.
Basslink,
at 370km long, is the world’s second
longest subsea electricity interconnector with a nominal capacity to export 594
MW from Tasmania to Victoria, and import 478 MW. It cost $874 million to build and
was commissioned in April 2006. It’s owned by Basslink P/L a subsidiary of
Keppel Infrastructure Fund listed on the Singapore Stock Exchange and part
owned by the Singapore Government. Basslink P/L is currently in Receivership
looking for new owners. Basslink is part of NEM but is an unregulated link.
On the other hand,
both Murraylink and Directlink are regulated interconnectors. Both started as
unregulated links but swapped because life was too difficult. Both were
unviable as unregulated links. Becoming regulated means spreading the costs
amongst a wider number of network users.
Basslink P/L was not a
true MNSP Merchant Network Service Provider, as unregulated links are often called,
because of the exclusive arrangement with Hydro which entailed the payment of
an agreed facility fee which removed most of the trading risks from Basslink
P/L. Murraylink and Directlink didn’t have sugar daddies when trying to survive
as unregulated interconnectors. Basslink is about to experience what life is
like without a regular facility fee.
Prices that can be
charged by regulated interconnectors are determined by AER, the Australian
Energy Regulator. This is no different to TasNetworks’ transmission and
distribution networks, both of whose prices are regulated by AER via price
determinations every five years.
Murraylink is an interconnector between
South Australia and Victoria. approximately 176 kms long, rated at 220MW and
commissioned in 2002 at a cost of $177 million. It is currently owned by Energy Infrastructure Investments Group EII, but
operated by APA. The ownership of EII is
split between APA with 19.9%, Japan-based Marubeni Corporation with 49.9%, and Osaka Gas with 30.2%. APA is an ASX listed company which has
recently bought $99 million worth of Basslink P/L’s debt, for a price likely to
have been less than the face value of the debt, but which gives APA a seat at
the table when discussing future ownership of Basslink with the Receivers.
The
main transmission service providers in each region are ElectraNet in SA and
AusNet Services in Vic. How the system of regulated interconnectors work can be
gleaned from AER’s determinations The following cut and paste from page 10 of Murraylink determination discusses the expected
impact of the regulated price for the Murraylink interconnector on residential
electricity bills.
The annual electricity bill for customers in
each region in the national electricity market will reflect the combined cost
of all the electricity supply chain components – wholesale generation costs,
transmission and distribution network costs, the retailers’ costs and profit
margin, and the cost of environmental policies including subsidies for
renewable energy, such as solar feed-in tariffs. The transmission network
charge component of electricity bills for SA and VIC represent about 9 per cent
of an average customer's annual electricity bill in SA and about 6 per cent in
VIC.
Murraylink’s
network charges are built into transmission charges in SA and VIC. The main
transmission service providers in each region (ElectraNet in SA and AusNet
Services in VIC) take a portion of Murraylink’s allowed revenue in developing
the applicable transmission charges to apply to and collect from customers in
their respective regions. Murraylink is then compensated by ElectraNet and
AusNet.
Murraylink
is a small component of the broader transmission networks that serve SA and
VIC. This small proportion explains the modest impact this final decision on
Murraylink is likely to have on average annual electricity bills in SA and VIC.
Murraylink’s
value as determined by AER for price setting purposes, it’s RAB or Regulated
Asset Base, is around $120 million. What it may have cost to build ($177
million) is irrelevant. AER determines a price based on what it reckons the
asset is worth. For comparison purposes TasNetworks’ transmission RAB is valued
at $1,287 million and its distribution assets at $1,737 million. In simple
terms AER allows providers to make returns on regulated assets after allowing
for expected expenses including capital upgrades. The current returns are
around 5 per cent pa. Distribution costs are between three- and four-times
transmission costs
In
the case of Murraylink the value of the link is only $120 million. Hence there
is not a huge impact on electricity prices in Vic and SA, the two connected
States. As AER noted:
The
transmission network charge component of electricity bills for SA and VIC
represent about 9 per cent of an average customer's annual electricity bill in
SA and about 6 per cent in VIC.
Directlink
is a smaller interconnector designed to link northern NSW with southern Queensland,
59 km in length and commissioned in 1999 at an estimated cost of US$70 million
with a total rating of 180 MW. Directlink’s RAB is currently about $145 million.
Directlink
is also owned by EII, the same as Murraylink. APA is the operator. Given that
APA has indicated it sees Basslink’s future as a regulated interconnector, it
wouldn’t be hard to visualise Basslink with the same owners as Murraylink and
Directlink, and all operated by APA. The termination of the BSA makes this
possibility much more likely. Basslink will struggle to survive as an
unregulated asset, just as Murraylink and Directlink did, now that Hydro has
stopped propping it up with the monthly facility fee.
When
Basslink becomes a regulated asset, the AER will assess the value of its RAB
which will determine how much will be paid to Basslink’s new owners. This
amount will be recovered from network users in the same way as for Murraylink,
described above. The issue for Marinus is whether agreement can be reached to
enable Marinus’ costs to be recovered for all net work users. At this stage
other States aren’t keen for their electricity users to fork out for Marinus
Meanwhile
Marinus is not the only new interconnector on the NEM drawing board. Humelink a
proposed interconnector in NSW is facing the same hurdles as Marinus. These
were laid out in detail by Bruce Mountain, Ted Woodley and Hugh Outhred in a recent article in Renew Economy.
Specifically
the authors said:
Those in favour of projects in the Report (AEMO’s
2021Transmission Cost Report) and in the Integrated System Plan (ISP)
invariably suggest that AEMO’s inclusion of such projects amounts to an
endorsement of their economic benefit.
However, AEMO’s ISP is a system-wide expansion
study in which committed generation projects are taken as inputs.
This means that in the assessment of HumeLink, for
example, since Snowy 2.0 is deemed to be committed, the ISP treats this as a
sunk cost.
But of course Snowy 2.0 and HumeLink are
intertwined complements. Like a train station and a train line, the one has
much less value without the other. Treating one as “committed”, biases
the decision to commit the other.
To address this, in evaluating the economic merit
of HumeLink, it is therefore essential to include the cost of Snowy 2.0.
AEMO does not do this – as explained Snowy 2.0 is treated as a committed
project and so its costs are ignored in the ISP’s analysis of HumeLink.
This means that AEMO’s analysis can not conclude that
HumeLink is an economically sensible transmission expansion, it can only
conclude that having ignored the costs of Snowy 2.0, its model finds that
HumeLink is necessary in order to not waste the storage potential of Snowy 2.0.
This fundamental modelling issue is not widely
understood. It is important that it is, since the inclusion of projects
such as HumeLink in AEMO’s ISP is treated by influential but distant actors –
such as parliamentarians – as credible proof of endorsement.
Considering the importance of AEMO’s position on
power system development, it is essential that AEMO states more clearly the
basis upon which major augmentations such as HumeLink and Marinus Link are
included in its development plans, and how the economic merit of such inclusions
should be understood.
The case for Marinus stacks up, so
we’re told, because there’ll be 200 per cent of renewables looking for a market.
At the same time the case for 200 per cent renewables makes sense because there’ll
be a 1500 MW cable ready to transport electricity to mainland markets. Marinus
is needed so we’re told, to be able to export all the surplus wind power, which
coincidentally is only being built to take advantage of Marinus. It’s an
intellectually dishonest, self-fulfilling circular proposition.
If the 200 per cent renewables
projects and Marinus were considered as one project requiring a viability
assessment before proceeding, they wouldn’t be built. It would have already
happened if they were viable.
Instead we have a system, a
conspiracy of subterfuge, which is the only way that otherwise uneconomic
projects can proceed. This system is supported by two other dodgy factors. The
first of those is being able to ignore a range of costs by treating them as
sunk costs and therefore not relevant when assessing project viability. The
second is being able to have the relevant assets accepted as regulated assets thereby
guaranteeing participants guaranteed income over a longer period. That’s the
prize being sought. Any public policy errors are papered over with sunk costs
and guaranteed income streams.
Both Murraylink and Directlink were
nonviable as unregulated assets. They both needed to become regulated and have
all network users help give them a return.
On the matter of sunk costs, it mustn’t
be forgotten that being categorised as such doesn’t mean they don’t have to be
paid. It only means they can be ignored when assessing project viability.
Basslink had sunk costs. The Expert Panel which reported on Basslink in March 2012
explained how the $50 million deposit paid by Hydro when Basslink was being
built and all the hedging arrangement entered into during constructions were
treated as sunk costs and ignored when assessing the project viability. Yet Hydro
is still paying the $150+million of construction hedging arrangements incurred
prior to 2003. These are included in the monthly fee paid to Macquarie Bank .
They may be sunk costs but they still impact Hydro’s cash flow.
A grand plan or a hotpotch of
competing interests?
The major problem with providing
promoters an opportunity to treat project costs as sunk costs is that it
encourages aberrant behaviour. If that’s not moral hazard on steroids then what
is? If a viable project results, it will be by good luck rather than sound
planning. The authors of the Renew Economy paper further explain the problems
with projects like Marinus:
The fundamental commercial driver for transmission
companies is to maximise revenues through building more regulated assets.
Hence, there is an inherent incentive to underestimate costs to get a project
to the proposal stage.
History bears this out. We are unaware of any
transmission project where the cost decreased after the initial estimate.
Naturally, a project develops momentum as it
progresses, and it becomes more difficult to stop, even with the inevitability
of escalating costs and decreasing (even negative) net benefits.
Estimated costs need far more scrutiny, right from
the initial stages of a proposal, and some form of reprimand when shown to be
understated.
History certainly does bear this out. Basslink at
$874 million cost double its original estimate. And that figure doesn’t include
the $150+ millions of sunk costs conveniently overlooked.
Having assets that will be regulated is the key. Regulated
returns where costs are borne by all network users is a big attraction.
Marinus’ major proponent, TasNetworks is beastly
careless how much Marinus will cost as it won’t have to fund it. Any addition
to its RAB is always welcome as it means more guaranteed income which all
network users will pay.
TasNetworks’ position highlights the inherent conflicts
between all parties…. the government, Hydro as the major generator, TasNetworks
as the transmission company, private investors hoping to step in and build more
generation assets to reap the rewards of guaranteed income streams and
consumers looking for lower prices. It is highly unlikely that the conflicts
will be satisfactorily resolved as the Minister in charge in is Guy Barnett,
someone who is yet to come across a problem that wasn’t the fault of his
political opponents, and every proposed solution is disingenuously described as
being in the best interest of all Tasmanians. And by the way, there’s no such
thing as a subsidy. Anything that gives a return can’t be a subsidy if evidence
given by Mr Barnett to the recent parliamentary hearing into government
electricity businesses is any guide.
However, we are starting to see conflicts play out.
TasNetworks has received grants to explore/justify
Marinus’ viability knowing it won’t have to fund it and knowing that any
increase in its RAB with more on-island transmission assets will be given a
regulated price by AER which will enable it to get the necessary funds from
Tascorp to construct the assets. Abundant moral hazard rarely leads to sound
public policy decisions.
The government insisted Hydro sign a power purchase
agreement PPA with the Granville Harbour Windfarm. Hydro was obviously
unimpressed because it lists the subsidy given to Granville as a Community
Service Obligation alongside support for Cricket Tasmania and the Hobart
Hurricanes. Why would Hydro as a generator be interested in subsidising another
generator? It makes a semblance of sense for a retailer like Aurora Energy to
enter into PPA with a windfarm like it did with Cattle Hill, but to insist
Hydro as a generator do so suggests heavy handed meddling by the government.
The PPA between Hydro and the Woolnorth Wind Farm
WWF signed to facilitate the 2014 sale of 75 per cent of WWF to Shenhua , a
Chinese State-owned company (Hydro retains the remaining 25 per cent) disguises
an ongoing subsidy to WWF. In its latest reporting year, the 2020 calendar
year, WWF received a $14.66 million subsidy from Hydro for purchases of
electricity and an estimated $15 million for the purchase of large scale
renewable energy certificates LGCs . That’s a total of $30 million. The cash
dividend for the year received by Hydro from WWF was only $4 million. Hence
Hydro’s 25 per cent share in WWF produced cash losses of $26 million. Then
there’s the non-cash effects. At the end of the 2020 reporting period WWF
listed the future benefit of the deal to sell LGCs to Hydro as being worth $96
million. That means there must be a corresponding liability in Hydro’s books of
a similar amount. It’s included in Hydro’s onerous contracts which were listed
as a liability totalling $240 million at 30th June 2021. Different
accounting rules apply to the treatment of LGCs and electricity purchases. The
former are financial assets and need to be valued at fair value each year. The
expected value is recorded as an asset (or liability) and any movement recorded
in the P&L each year. Electricity purchases on the other hand are recorded
when the purchase occurs. Hence expected subsidies of future electricity
purchases aren’t recognised until electricity is delivered. Now $96 million,
the estimated future subsidy to WWF via LGC purchases (NB the agreed purchase
price is greater than the expected market price of LGCs. Hydro will make future
losses buying LGCs from WWF at an agreed price and on-selling them in the
market for less) may not be a particularly large figure but in balance sheet terms
it’s 5 per cent of Hydro’s equity. It also means Hydro’s interest in WWF which
is listed as being worth $71 million, actually has a negative value of $25
million. Heaven forbid if Senator Abetz ever finds out his electricity bills
are subsidising the Chinese government. (More info on WWF’s PPA is presented
below in the section Who will benefit?)
It’s all very well to say an onerous contract was
not onerous at the time it was signed but risk managers should have pointed out
the problem that if a PPA does become onerous and requires Hydro to find cash,
it is likely to occur at the same time as Hydro will itself be feeling cash
flow pressures. As Hydro reaches into its pockets to satisfy the onerous
contracts it will likely find there’s less cash there for the exact same
reasons as caused the PPA to become onerous, viz a fall in electricity spot and
LGC prices. A double whammy. Government policy of propping up other generators via
PPAs can only ever undermine Hydro. It is little wonder Hydro is under
increasing pressure. Governments encouraging others to feast at Hydro’s table
looks like a dumb idea.
That didn’t stop the government from giving public
support to Twiggy Forrest’s desire to buy a sizable chunk of Hydro’s electricity
for his proposed hydrogen plant, possibly as much 20 per cent of Hydro output
which is around 9,000 GWh pa, at a giveaway price of $20 per MWh, as was
reported by ABC reporter Emily Baker. .If Hydro
could otherwise sell the power for $45 per MWh that amounts to a subsidy of $25 per MWh. 2,000 GWh means the subsidy amounts to $50 million pa. Fortunately,
Hydro seems to have resisted government demands to subsidise Twiggy to that
extent. Hydro’s Ian Brooksbank was reported as saying Hydro’s role in
supporting the possible hydrogen industry in Tasmania would be via the
provision of a “firming” service, to fill the gaps which may occur with the
erratic nature of electricity from wind. To not have resisted would have meant Twiggy
would have eaten most of Hydro’s lunch, a dumb idea given its unique suite of
assets.
All the
above serves to emphasise that there are a host of conflicting interests in the
electricity space which Minister Barnett tries to pretend can all be satisfied
by the 200 per cent renewable target/Battery of the nation/Marinus/ hydrogen/Jobs
jobs jobs/lower prices leaving everyone being better off. It’s a silly notion.
There will be winners and losers who need to be identified before we reach the
point of no return, which the campaign of misleading information and unsubstantiated
assertions appears designed to achieve before people realise the full
implications of the grand plan.
Who will
benefit?
The
government’s 200 per cent renewable energy goal will require more wind farms
plus a new connector. It may be useful to have a closer look at a current wind
farm operation and at Basslink to understand where money comes and goes. The
publicly available financial statements for WWF, which produces about 1,000 GWh
pa or about 10 per cent of our needs, and for Basslink P/L, the owner operator
of Basslink (currently in Receivership) are an essential starting point to
understanding the $s involved.
First
let’s look at WWF. The latest financials are for the calendar year ending 31st
Dec 2020. The following is the profit and loss statement:
A healthy
profit of $132 million is evident in the latest year, not bad for a company
with net assets of $264 million. Most of the profits are attributable to subsidies
from Hydro. Specific items needing a closer look are sales revenue, operating
expenses, and fair value gains.
This is
the breakup of sales revenue:
Energy
sales relates to electricity. Environmental energy products are large scale
generation certificates LGCs. Both are covered by PPAs with Hydro.
In the
2020 year WWF produced 1,036 GWh of electricity. 2019 was a windier year
producing 1,205 GWh (These figures are from NEM figures posted on Wiki). This
suggests LGCs are bought at a contracted price of around $46 per LGC. (NB One
MWh creates one LGC meaning one GWh produces 1,000 LGCs and 1,000 GWh produces
1,000,000 LGC. LGC prices have fluctuated between about $20 and $90. Currently
they are in the low $30s).
In the
case of electricity sales, the revenue fall over the 2 years is quite striking.
From approx $75 per MWh to $33 per MWh. These are the gross amounts obtained by
selling through NEM. These aren’t the
net amounts that WWF end up with after the PPA agreement with Hydro. To work
out the net amount one needs to look at the breakup of operating expenses. This is the relevant snapshot:
As can be
seen in the 2019 year WWF paid $33 million to Hydro as a result of the PPA, and
in 2020 it received $14.6 million (the receipt is shown as a negative expense).
That
means, in net terms, WWF received $57 million in 2019 and $49 million in 2020,
round about $46 per MWh in each year. When the market price is below that
figure Hydro pay WWF. When the reverse occurs, WWF pays Hydro. That’s how PPAs
work.With more wind coming on line, spot prices will likely fall meaning Hydro
will be subsiding WWF until the deal expires in 2028.Ouch.
Altho’
both electricity and LGCs are covered by a PPA they are treated differently in
the financial statements. Electricity sales are treated just like any goods and
services are treated by any business. Sales are recorded at the time of sale.
Any possible future subsidy is ignored. There is not sufficient certainty as to
the amount of the future subsidy. The actual subsidy only becomes apparent at
the time of sale. This is why the power purchase agreements with major
industrials in Tasmania which accounts for almost half of Hydro’s total sales
(in quantity terms) do not appear as onerous contracts in Hydro’s books The
sales of electricity to major industrials are recorded at the time of sale and
no provision is made in the financials for possible future contracted
subsidies. (altho’ they may be indirectly included when generation assets are
valued based on future income.)
LGC’s on
the other hand are financial assets. A PPA which includes financial assets need
to be valued each year for accounting purposes. The future expected subsidy to
be received for LGCs needs to be estimated. Changes over a year are recorded as
fair value changes in the P&L, with the value at the end of the year included in the
balance sheet as an asset. In 2020 WWF included $106 million as a fair value
gain for the year. This was the change in the fair value of LGCs for the year.
At the end of 2020 WWFs financial asset re LGCs was recorded as $96 million.
This represents what WWF expects to receive from Hydro for LGCs over and above
the market price. In other words, the expected future LGC subsidy from Hydro.
From
Hydro’s viewpoint it records a similar figure as a liability, viz the value of
the onerous contract with WWF.
In 2020
the subsidy re electricity was $14.6 million. This was actually paid. In the
case of LGCs the subsidy was also paid and included in LGC sales of $47.9
million. It is likely to have been approx $15 million for the year.
Hence the
PPA with WWF meant Hydro subsidised WWF to the tune of $30 million for the
year. That’s to produce roughly 1,000 GWh or 10 per cent of Tasmania’s annual
needs. How much will it cost in subsidies if the 200 per cent renewable target
is reached?
The
operating expenses detailed above indicates the relatively small level of operating
expenses, the flow on costs which spruikers of projects often use to hype their
projects. Consultant/contractor costs are $11 million. This will comprise both
labour and materials. The local component will only be a fraction of this. In
the case of employee expenses, they totalled $4.4 million in 2020. But WWF
reported to ASIC there were only 6 employees. The only conclusion is that they
earned on average $750k for the year. They’re unlikely to be locals paying
Tasmanian payroll taxes and drinking at the pub in Smithton.
The flow
on benefits from wind farm operations are relatively small. Most wind farms are
either owned by foreigners or interstate investors (in the case of Granville) so
income ends up in their hands after bankers grab whatever is owing to them.
The meagre
benefits that trickle down from interconnector businesses are similar to
windfarms. Take a look at Basslink’s latest P&L:
This is
the year that recorded the costs of Basslink’s legal outcomes with Hydro. There
are lots of non-recurring entries.
The loss of
$96.6 million highlights BL’s problems which led to a Receiver being appointed
BL had to
write off $30.8 million in facility fees which it had previously included as
income, but Hydro had refused to pay following the 2015/16 cable outage. The
revenue was accordingly reduced from $84 million to $53 million.
General
& admin costs of $90 million include all the compensation payable to Hydro and
the State of Tasmania (not all was paid during the year), plus BL’s legal
costs.
Fair
value losses of $15.5 million and finance costs of $26 million relate to the
costs of Basslink Groups’s finance costs for the year.
Operating
outlays were minor. Network and maintenance costs were $2.8 million and employee
costs were $4.2 million. There were 21 employees, so they averaged $200k each
pa. Not too bad if you can’t get a job at WWF. A few may have been locals. The trickle-down
effect into the local economy wouldn’t have been much more than from a neighbourhood
milk bar. The downstream effects of windfarms once built are negligible.
There’s little there for locals. Absentee owners bankers and other paper
shufflers snaffle most of the lucre.
There’s
absolutely no reason for thinking the downstream effects of a new
interconnector and a landscape full of windfarms will produce a different
result. Saving the planet provides a very convenient camouflage for the self-interests
of a few.
Termination
of the Basslink Services Agreement BSA
On the 10th
February Hydro put out a media release:
Hydro Tasmania confirms it has terminated the Basslink Services
Agreement (BSA) as announced by the Minister for Energy and Emissions Reduction
today.
Hydro Tasmania remains willing to discuss with receivers an alternative
commercial model that could include key elements of the BSA, that would provide
funding during the receivership and help transition the asset to an alternative
commercial model.
Consistent with this Hydro Tasmania has made a good faith offer to the
Receivers for an interim arrangement, under which the key elements of the BSA
would be put back in place for one month whilst the parties discuss possible
alternative arrangements.
The Minister for Energy and Emissions Reduction’s
announcement on the same day said:
Consistent with the Tasmanian Government and Hydro
Tasmania’s decision in November last year to protect and progress Tasmania’s
legal rights in relation to the Basslink cable, Hydro Tasmania has taken
another step in that process terminating the Basslink Services Agreement (BSA).
This follows the 2020 arbitration concerning the
cause of the 2016 major Basslink outage, which found in the State and Hydro
Tasmania’s favour, confirming the link cannot meet the capacity requirements
set out in the BSA and that the owner of Basslink should pay compensation to
the State.
Since November last year, Hydro Tasmania along with
the State, has been in negotiations with the receivers of Basslink regarding an
alternative commercial arrangement.
The termination of the BSA will not impact
Tasmania’s energy security, which remains on firm footing, with very strong
hydro storage levels, the Cattle Hill and Granville Harbour wind farms, while
the cable will remain in service.
The Tasmanian Government and Hydro Tasmania will
continue to engage with Basslink's financiers and receivers on alternative
commercial arrangements, suitable for the receivership period.
Tasmanians can be assured that our energy security
is stronger than ever and that the Government will continue to act in the best
interests of Tasmanians.
Lat’s try
to make sense of this:
The actual
default by BL which gave Hydro room to terminate the BSA is not clear…..
whether it was the arbitrator’s findings about the cable’s shortcomings or
due to the appointment of a receiver or because the Receiver intends to sell
the cable to another party, it’s not clear. All may be grounds for default by
BL which then allowed Hydro to quit the agreement.
With the
termination of BSA, BL’s Receivers will retain the ongoing inter-regional
revenues IRR and Hydro will cease paying the facility fee.
In most
months the IRR is less than the facility fee so Hydro will be better off.
BL will
continue to buy Hydro’s electricity if it wishes to export but the profits from
the deal will belong to BL. Likewise electricity will still be imported by BL.
It is not
clear what will happen to the arrangements with Macquarie Bank MBL currently
costing about $4 million per month. Part of what Hydro pays MBL each month
relates to the sunk costs incurred pre 2003 so no doubt they will still need to
be paid, but part relates to the hedging arrangements re the interest rate component
of the facility fee. If the facility fee ceases to be payable what happens to
the facility fee swap arrangement with MBL? Another lawyers picnic?
The
Basslink Group owes financiers approx. $640 million. It’s actually not on BL’s
books, rather it’s owed by an associated company called Premier Finance Trust
Australia. What is on BL books is an interest swap arrangement designed to
hedge interest rates on the Group’s borrowings. Interest rates have fallen so
the latest fair value of the hedging arrangement shows a further liability of
$162 million. That’s an estimate of the amount needed to quit the hedging deal.
BL also
has a liability of $23 million labelled Provision for decommissioning costs,
which is an estimate of the costs needed to clean up at the end of the cable’s
life.
Another of
BL’s liabilities is the amount still due to the Tasmanian government of approx.
$50 million following successful legal action.
There is
also a $50 million deposit paid by Hydro to BL back in 2003 which was to be offset
against the facility fee payable from 2029 onwards. If the fee is no longer
payable, what happens to this deposit?
The
messiness of BL’s financials suggests it is unlikely that anyone will buy the
company as a way to acquire the cable. Instead, what will likely happen is the cable
itself will be sold.
The BSA
had another 10 years to run at the time it was terminated. At that time BL’s
income was via the facility fee from Hydro of approx. $85 million pa, which gave
BL an EBITDA (earnings before interest
tax depreciation and amortisation) of roughly $50 million . With the facility
fee being government guaranteed the earnings multiple may have been as high as
10 times giving BL (or at least the cable) a value of $500 million.
However
with the termination of the BSA, the cable’s income will be the inter-regional
revenue and that is a riskier proposition which further means a lower earnings
multiple will be needed to calculate the cable value. If the IRR is estimated
to be $70 million pa, that makes the EBITDA $35 million. Applying a 7 times
earnings multiple gives the cable a value of $245 million.
The
termination of the BSA means the cable is now an unregulated asset without a
guaranteed monthly facility fee which means it’s value could fall by as much as
50 per cent.
By
terminating the BSA Hydro will also have given up any pre-emptive rights it may
have had to acquire the cable should it be sold. But because it (and the Tasmanian
government) are still owed money by BL, it still has a place at the negotiating
table to discuss BL’s future.
For the
cable to become a regulated asset a new owner will have to be found. It’s
likely APA will be involved. It doesn’t make much sense for Hydro to have a
share. That only made sense if the BSA remained intact for another 10 years,
and Hydro ended up paying the facility fee to itself.
It would
make more sense if TasNetworks ran BL, but it is hellbent of trying to get Marinus
to the start line.
Whatever the value of the cable for the new
owner, its likely Regulated Asset Base RAB will end up being roughly similar
once the cable becomes a regulated asset. That in turn will underpin how much the
new owner will receive as a regulated asset.
Which
still leaves the big unknown….. how will Marinus be regulated? How much and who
will pay? It is likely that whatever
Marinus ends up costing, if the estimated cost is currently $3.5 billion, the
final cost will be well in excess of that figure, how much will the value of
its asset base be for the purposes of determining the cost burden on all
network users. The RAB figure will be far less than the cost, that’s for sure.
Which means that much of Marinus’ cost will be immediately written off. It’ll
be reminiscent of Tas Irrigation which builds water infrastructure. Using a
very rough rule of thumb, for every $3 spent on new works, $1 is recouped from
the sale of water rights, $1 of value remains on TI’s balance sheet being the
value of the asset which earns money from water rights holders each year and $1
is written off. In the case of TI there are arguably spill over benefits (forgive
the bad pun) from building new water infrastructure. The growth of industries
which benefit from the new water justifies the community’s investment in an
asset which loses 33 per cent of its value as soon as it is built.
For
Marinus the picture won’t be anywhere near as rosy. The likely spin off
benefits of Marinus and new wind farms, as shown above by examining the affairs
of existing wind farms and interconnectors are likely to be considerably less.
For a State facing momentous fiscal challenges it would be reckless to spend so
much for the benefit of so few.
What is
quite extraordinary is that the latest BL financials cheerily expected the BSA
to last until 2072. But barely a few months later, the cable may only be worth
25 per cent of its original $875 million cost, after a mere 15 years of life.
Yet we
are contemplating doing the same again, going down the same path, without the
slightest interest in learning any of history’s many lessons.
(updated 21st Feb to correct a typo)
Good article John. Can I suggest writing an Executive summary for those that don't have the time or patience to read the entire article?
ReplyDeleteIt's like someone turning on the light. I'll need to read it again (and again) but it fills all the gaps in my understanding of the smoke-and-mirrors stuff the 200% TRET contains.
ReplyDeleteIs the system too complicated? Are politicians responsible for that? Who said keep it simple stupid?
ReplyDeleteWe have Basslink cable, Battery of the nation cable proposed at huge cost & gas pipeline in Baltic sea fractured, maybe by sabotage. Plenty of solar waiting to be harvested. Then there is concentrated solar to harvest too with heliostats.
As Europeans pay massive energy bills in winter we could put PV on our rooftops for maybe one or two years of those energy bills.